9 votes
1 answer 349 views
Salam Sejahtera, Saya sekadar ingin bertanya Mengapa Kakitangan yang diarah berpindah/tukar cawangan diberi surat amaran menggunakan kuasa luar sedangkan kakitangan terbabit tidak tahu menahu mengenai rayuan yang dikemukakan oleh pihak luar itu. Sebagai contoh pegawai ... kawan saya yang merasakan ketidakadilan. Saya harap ianya tidak berulang agar keharmonian rumah tangga JKR dikekalkan. Sekian
asked Feb 25, 2014 in Human Resource Management mshahlanfitry 230 points 2 4
19 votes
5 answers 347 views
If you can’t see the whole picture… you can’t appreciate BIM. Hard to believe…perhaps to some… but many /most of us in the Architecture, Engineers, Construction, Owners, Operations sector still don’t know how to define BIM.
asked May 26, 2014 in BIM Mohd Fairuz 27,310 points 73 158 200
11 votes
1 answer 339 views
27 votes
3 answers 336 views
Adakah terdapat option (cadangan) lain selain pengkorporatan JKR sepenuhnya?
asked Jan 28, 2019 in Stakeholders Management firdauswazir89 350 points 3 4 7
21 votes
8 answers 318 views
Bagaimana untuk mengelakkan EOT bagi sesebuah projek?
asked Sep 28, 2016 in Contract Management shdzain 15,580 points 20 41 115
15 votes
1 answer 315 views
Fom reading McKinsey Global Institute’s (MGI) report,... "Big Data: The next frontier for innovation, competition, and productivity, that big data is now recognized as an important factor of production, alongside labor and capital." Boleh kita bincang-bincangkan
asked May 26, 2014 in Project Management Mohd Fairuz 27,310 points 73 158 200
22 votes
1 answer 314 views
Ini penting untuk penambahbaikan pengurusan projek berdasarkan kepada kos, quality, time dan mungkin produktiviti juga. Adakah JKR telah mempunyai "tools" bagi pengukuran ini. OBB yang dilaksanakan sekarang ini macamana? "Return on investment" juga?
asked Jul 2, 2014 in Project Management Mohd Fairuz 27,310 points 73 158 200
24 votes
3 answers 311 views
asked Mar 23, 2015 in Electrical nurafidah 410 points 2 4 5
9 votes
2 answers 310 views
5 votes
2 answers 307 views
To avoid time at large and also the need to update the SKALA. , as suggested by the J/K EOT, Non Completion Certificate (NCC) was issued since the application for EOT No 2 was not fully substaintiated with enough evidence.After 2 months on LAD, EOT No 2 ws finally ... . How best to address this issue? (Start/end dates for EOT No.2? New NCC needed? LAD collected already deposited into Akaun Hasil?)
asked Nov 17, 2013 in Civil norshimah 6,610 points 3 31 57
20 votes
7 answers 302 views
asked Dec 20, 2013 in Stakeholders Management wanzul 220 points 1 2 3
24 votes
4 answers 294 views
13 votes
3 answers 290 views
In designing a rainwater harvesting system if we provide tanks on the ground level, we would have to provide a proper pumping system to use the water harvested - here there is additional cost involved in providing the pumping system and also the electricity cost. There ... a separate structure (surely more expensive). Has any study been made to find out which of the system is more cost effective?
asked Mar 21, 2014 in Building harjit 7,620 points 12 29 53
17 votes
1 answer 290 views
Salam. Mohon bantuan dari CPK terutamanya, tuntutan perjalanan menggunakan kenderaan sendiri saya telah ditolak oleh bendahari SUK menghadiri temuduga CBBP/HLP Anjuran CPK JKR HQ bagi menyambung pengajian di peringkat Master(saya di JKR State). Temuduga ini diwajibkan ... telah dilampirkan. Surat panggilan temuduga CPK juga. Mohon bantuan dari Bahagian Kewangan lain di JKR Negeri lain. Tqvm.
asked Mar 2, 2014 in Human Resource Management mfairuz 9,540 points 25 58 109
16 votes
2 answers 289 views
Berapakah kadar arus baki kebocoran yang dibenarkan bagi RCCB untuk pemasangan di tempat basah atau berair seperti bilik mandi, ruangan basah, kolam renang dan kolam pancutan?
asked Nov 21, 2013 in Electrical sabrimd 6,610 points 22 55 80
14 votes
3 answers 284 views
Jkr as world class service provider...has we done our benchmarking to this statement? No doubt our spec and std are refered to by many but looking into our practices many still doubted it..agree or disagree?
asked Dec 3, 2013 in Project Management abrahmans 9,180 points 17 34 86
...