11 votes
51 views
in Technical & Contract Admin 690 points 3 4 13

1 Answer

4 votes
Ada dinyatakan dalam JKR Spec 2014 or 2005.

Untuk JKR Spec 2005
Boleh refer
Page D/11
5.5 Placing
5.5.1 Placing in Dry Condition
"For all concrete whether mixed on or off the site of the Work, each batch shall be
placed and compacted within two (2) hours of adding the cement to the dry
aggregates and within 45 minutes (or any other period of time based on the trial
mix as per 2.4, 3.2.3 and approved by the S.O. if an admixture is used) of adding
water to the cement and aggregate. Concrete shall not be placed in any part of
the structure until the approval of the S.O. has been obtained. If concreting is
not started within 24 hours of approval given, approval shall again be obtained
from the S.O."
1,660 points 2 10 25
0
Terima kasih untuk maklumbalas tuan di atas.

Saya sedia maklum bahawa ayat di atas tidak pernah berubah sepertimana JKR/SPJ/1988 (fasal 9.5.4), JKR/1992 (fasal 5.4.1), JKR/2005 (fasal 5.5.1) dan JKR/2014 (fasal 4.7.1.1).

Yang saya paham untuk penerangan di atas ialah untuk konkrit sama ada dibancuh di dalam atau di luar tapak bina, setiap batch hendaklah di tuang dan dimampatkan dalam tempoh 2 jam setelah simen dan dry aggregate dicampurkan. Ini bermakna untuk plain concrete, bancuhan kering (tanpa air) diantara simen dan dry aggregate ini hanya dibenarkan untuk digunakan dalam masa 2 jam sahaja.

Dan apabila campuran simen dan dry aggregate tadi dicampurkan dengan air, ianya hendaklah digunakan dalam tempoh 45 minit.
...