Sebelum lay binder course, normally kita guna SS1K. But, boleh tak guna RS1K or RS3K? In this case, ada additional cost involved SS1K & bahaya kpd trafik sediada, kena tunggu 24 jam. For cases where there is no existing premix, can we just add cement not more ... the top layer 200 mm of the new crusher run. Kita reconstruct sebab subgrade CBR< 3, so, kita recon and reinforced with geotextiles.